Section 41-2-121 - Criteria for Water Development Projects; Disclosure of Personal Interests by Commission.

WY Stat § 41-2-121 (2019) (N/A)
Copy with citation
Copy as parenthetical citation

41-2-121. Criteria for water development projects; disclosure of personal interests by commission.

(a) The water development commission shall establish criteria for evaluation and administration of water development projects. Criteria shall include but not be limited to the following:

(i) All water development proposals submitted to the legislature shall be reviewed by and accompanied by the recommendation of the water development commission;

(ii) The commission's recommendation shall:

(A) Emphasize projects developing unappropriated water;

(B) Give preference wherever possible to projects developing new storage capacity;

(C) Consider the potential for development of hydroelectric power in any project through Level II;

(D) Include a summary of the commission's findings under W.S. 41-2-112(b);

(E) Include financing methods subject to the following:

(I) Any water development project may be financed by grants not to exceed seventy-five percent (75%) of the total cost of the project;

(II) Storage projects may be financed by grants for the full cost of the storage capacity but not to exceed public benefits as computed by the commission;

(III) Loans may be made for domestic, municipal, agricultural, industrial, recreational or fish and wildlife enhancement purposes;

(IV) The term of a loan shall not exceed fifty (50) years after substantial completion of a project;

(V) Payment of interest and principal on loans may be deferred for not more than five (5) years after substantial completion of the project;

(VI) Loan contracts for project construction shall include provisions to ensure [that] the project shall be operated and maintained during the term of the loan;

(VII) The state may elect to own all or a part of a project and enter into water service repayment contracts with project developers;

(VIII) A project involving a transbasin diversion shall address the impact of the diversion and recommend measures to mitigate any adverse impact identified in the basin of origin;

(IX) Interest on a loan should provide a reasonable return to the state but shall not be less than four percent (4%) except when the commission recommends a lower interest rate because of public benefits;

(X) Loan contracts for project construction shall provide for payment of interest on defaulted payments at a rate of ten percent (10%) per annum.

(iii) Repealed by Laws 1986, ch. 109, § 3.

(iv) The commission may disqualify from consideration or give lower priority to a project proposed to correct problems identified in a review performed by the department of environmental quality under W.S. 18-5-306(c) where the board of county commissioners approved a subdivision application notwithstanding the department's recommendation that the application be disapproved.

(b) Any member of the commission who has a personal or private interest in any matter proposed or pending before the commission shall publicly disclose this fact to the commission and shall not vote thereon.

(c) Within sixty (60) days after the effective date of this subsection or within sixty (60) days following appointment and annually on or before January 1, each member of the commission shall file written disclosures relative to all interests held by the member or the member's spouse, including interests in partnerships and corporations, with the secretary of state, of:

(i) Any water rights, permits or applications held, whether for direct flow, reservoirs or underground water;

(ii) Any interests in engineering or construction firms which engage in designing or constructing water projects.

(d) The promulgation of operating procedures and program criteria by the commission under this section and decisions of the commission relating to the recommendation, prioritization or disqualification of projects are specifically exempt from all provisions of the Wyoming Administrative Procedure Act including provisions for judicial review under W.S. 16-3-114 and 16-3-115.

(e) Prior to authorizing a water development project, the commission shall require each project sponsor to demonstrate that the entity has the authority to adequately assess fees or collect funds to cover operation and maintenance expenses related to the water development project. Any entity that does not have the authority or ability to collect sufficient funds for the operation and maintenance of the project may be required by the commission to establish an operations and maintenance account as provided in this section. The commission shall develop criteria related to the establishment of an operations and maintenance account which shall include:

(i) An operations and maintenance account shall only be required for project sponsors that have taken out a loan for any portion of the project expense and shall not be required after the loan has been repaid;

(ii) The funds required in any operations and maintenance account shall not exceed ten percent (10%) of the project cost.