RCW 64.38.070 Reserve study—Requirements.
(1) A reserve study as described in RCW 64.38.065 is supplemental to the association's operating and maintenance budget. In preparing a reserve study, the association shall estimate the anticipated major maintenance, repair, and replacement costs, whose infrequent and significant nature make them impractical to be included in an annual budget.
(2) A reserve study must include:
(a) A reserve component list, including any reserve component that would cost more than one percent of the annual budget of the association, not including the reserve account, for major maintenance, repair, or replacement. If one of these reserve components is not included in the reserve study, the study should provide commentary explaining the basis for its exclusion. The study must also include quantities and estimates for the useful life of each reserve component, remaining useful life of each reserve component, and current major maintenance, repair, or replacement cost for each reserve component;
(b) The date of the study, and a statement that the study meets the requirements of this section;
(c) The following level of reserve study performed:
(i) Level I: Full reserve study funding analysis and plan;
(ii) Level II: Update with visual site inspection; or
(iii) Level III: Update with no visual site inspection;
(d) The association's reserve account balance;
(e) The percentage of the fully funded balance that the reserve account is funded;
(f) Special assessments already implemented or planned;
(g) Interest and inflation assumptions;
(h) Current reserve account contribution rates for a full funding plan and baseline funding plan;
(i) A recommended reserve account contribution rate, a contribution rate for a full funding plan to achieve one hundred percent fully funded reserves by the end of the thirty-year study period, a baseline funding plan to maintain the reserve balance above zero throughout the thirty-year study period without special assessments, and a contribution rate recommended by the reserve study professional;
(j) A projected reserve account balance for thirty years and a funding plan to pay for projected costs from that reserve account balance without reliance on future unplanned special assessments; and
(k) A statement on whether the reserve study was prepared with the assistance of a reserve study professional.
(3) A reserve study must also include the following disclosure: "This reserve study should be reviewed carefully. It may not include all common and limited common element components that will require major maintenance, repair, or replacement in future years, and may not include regular contributions to a reserve account for the cost of such maintenance, repair, or replacement. The failure to include a component in a reserve study, or to provide contributions to a reserve account for a component, may, under some circumstances, require you to pay on demand as a special assessment your share of common expenses for the cost of major maintenance, repair, or replacement of a reserve component."
[ 2011 c 189 § 10.]
NOTES:
Effective date—2011 c 189: See note following RCW 64.38.065.