Section 1903 - Effect of timely protest or appeal.

UT Code § 63G-6a-1903 (2019) (N/A)
Copy with citation
Copy as parenthetical citation

(1) during the pendency of a timely: (a) protest under Section 63G-6a-1602; (b) appeal of a protest under Section 63G-6a-1702; or (c) appeal of a procurement appeals panel decision under Section 63G-6a-1802; and

(a) protest under Section 63G-6a-1602;

(b) appeal of a protest under Section 63G-6a-1702; or

(c) appeal of a procurement appeals panel decision under Section 63G-6a-1802; and

(2) until: (a) all administrative and judicial remedies are exhausted; (b) for a protest under Section 63G-6a-1602 or an appeal under Section 63G-6a-1702: (i) the chief procurement officer, after consultation with the attorney general's office and the head of the using agency, makes a written determination that award of the contract without delay is in the best interest of the procurement unit or the state; (ii) the head of a procurement unit with independent procurement authority, after consultation with the procurement unit's attorney, makes a written determination that award of the contract without delay is in the best interest of the procurement unit or the state; or (iii) for a procurement unit that is not represented by the attorney general's office, the procurement unit, after consulting with the attorney for the procurement unit, makes a written determination that award of the contract without delay is in the best interest of the procurement unit or the state; or (c) for an appeal under Section 63G-6a-1802, or an appeal to a higher court than district court: (i) the chief procurement officer, after consultation with the attorney general's office and the head of the using agency, makes a written determination that award of the contract without delay is in the best interest of the procurement unit or the state; (ii) the head of a procurement unit with independent procurement authority, after consultation with the procurement unit's attorney, makes a written determination that award of the contract without delay is in the best interest of the procurement unit or the state; or (iii) for a procurement unit that is not represented by the attorney general's office, the procurement unit, after consulting with the attorney for the procurement unit, makes a written determination that award of the contract without delay is necessary to protect the best interest of the procurement unit or the state.

(a) all administrative and judicial remedies are exhausted;

(b) for a protest under Section 63G-6a-1602 or an appeal under Section 63G-6a-1702: (i) the chief procurement officer, after consultation with the attorney general's office and the head of the using agency, makes a written determination that award of the contract without delay is in the best interest of the procurement unit or the state; (ii) the head of a procurement unit with independent procurement authority, after consultation with the procurement unit's attorney, makes a written determination that award of the contract without delay is in the best interest of the procurement unit or the state; or (iii) for a procurement unit that is not represented by the attorney general's office, the procurement unit, after consulting with the attorney for the procurement unit, makes a written determination that award of the contract without delay is in the best interest of the procurement unit or the state; or

(i) the chief procurement officer, after consultation with the attorney general's office and the head of the using agency, makes a written determination that award of the contract without delay is in the best interest of the procurement unit or the state;

(ii) the head of a procurement unit with independent procurement authority, after consultation with the procurement unit's attorney, makes a written determination that award of the contract without delay is in the best interest of the procurement unit or the state; or

(iii) for a procurement unit that is not represented by the attorney general's office, the procurement unit, after consulting with the attorney for the procurement unit, makes a written determination that award of the contract without delay is in the best interest of the procurement unit or the state; or

(c) for an appeal under Section 63G-6a-1802, or an appeal to a higher court than district court: (i) the chief procurement officer, after consultation with the attorney general's office and the head of the using agency, makes a written determination that award of the contract without delay is in the best interest of the procurement unit or the state; (ii) the head of a procurement unit with independent procurement authority, after consultation with the procurement unit's attorney, makes a written determination that award of the contract without delay is in the best interest of the procurement unit or the state; or (iii) for a procurement unit that is not represented by the attorney general's office, the procurement unit, after consulting with the attorney for the procurement unit, makes a written determination that award of the contract without delay is necessary to protect the best interest of the procurement unit or the state.

(i) the chief procurement officer, after consultation with the attorney general's office and the head of the using agency, makes a written determination that award of the contract without delay is in the best interest of the procurement unit or the state;

(ii) the head of a procurement unit with independent procurement authority, after consultation with the procurement unit's attorney, makes a written determination that award of the contract without delay is in the best interest of the procurement unit or the state; or

(iii) for a procurement unit that is not represented by the attorney general's office, the procurement unit, after consulting with the attorney for the procurement unit, makes a written determination that award of the contract without delay is necessary to protect the best interest of the procurement unit or the state.