Section 207 - Underground district.

UT Code § 54-21-207 (2019) (N/A)
Copy with citation
Copy as parenthetical citation

(1) the prohibition is reasonable and nondiscriminatory; and

(2) the authority: (a) (i) requires that all cable and utility facilities, other than an authority pole and attachment, be placed underground; and (ii) establishes the requirement in Subsection (2)(a)(i) more than 90 days before the day on which the applicant submits the application; (b) does not prohibit the replacement of an authority pole in the designated area; and (c) permits a wireless provider to seek a waiver, that is administered in a nondiscriminatory manner, of the undergrounding requirement for the placement of a new utility pole to support a small wireless facility.

(a) (i) requires that all cable and utility facilities, other than an authority pole and attachment, be placed underground; and (ii) establishes the requirement in Subsection (2)(a)(i) more than 90 days before the day on which the applicant submits the application;

(i) requires that all cable and utility facilities, other than an authority pole and attachment, be placed underground; and

(ii) establishes the requirement in Subsection (2)(a)(i) more than 90 days before the day on which the applicant submits the application;

(b) does not prohibit the replacement of an authority pole in the designated area; and

(c) permits a wireless provider to seek a waiver, that is administered in a nondiscriminatory manner, of the undergrounding requirement for the placement of a new utility pole to support a small wireless facility.