(1) Substantial compliance with the requirements of this chapter is sufficient to claim, as applicable, a preconstruction lien or a construction lien.
(2) Subsection (1) may not be construed to excuse compliance with or affect the requirement to file: (a) a notice of preconstruction service as provided in Section 38-1a-401 in order to claim a preconstruction lien; or (b) a preliminary notice as provided in Section 38-1a-501 in order to claim a construction lien.
(a) a notice of preconstruction service as provided in Section 38-1a-401 in order to claim a preconstruction lien; or
(b) a preliminary notice as provided in Section 38-1a-501 in order to claim a construction lien.