Sec. 5.403. RENEWAL PERIOD FOR CONSOLIDATED PERMIT. The renewal period for a consolidated permit issued under this subchapter is the shortest term set by any state or federal statute or rule governing one or more of the authorizations sought in the consolidated permit.
Added by Acts 1997, 75th Leg., ch. 1373, Sec. 1, eff. Sept. 1, 1997.
Sec. 5.404. RENEWAL OF PERMITS. A permit issued under this subchapter or a permit issued before and effective on September 1, 1997, that authorizes more than one permit program may be renewed, amended, or modified as a consolidated permit or may be separated by program and the permits may be processed separately and subject to the renewal, amendment, or modification requirements of applicable law governing operations at the facility, plant, or site.
Added by Acts 1997, 75th Leg., ch. 1373, Sec. 1, eff. Sept. 1, 1997.