§ 5-18B-44 Criteria for construction manager-at-risk engagement.

SD Codified L § 5-18B-44 (2019) (N/A)
Copy with citation
Copy as parenthetical citation

5-18B-44. Criteria for construction manager-at-risk engagement. Each qualification based request for proposals required by subsection 5-18B-43(2)(b) to enter into a construction manager-at-risk services contract where the construction manager-at-risk intends to actually perform construction on the project, shall meet the following criteria:

(1) The purchasing agency shall, prior to issuing any request for proposals to enter in a construction management services contract, establish and publish procedures for the solicitation and award of such contracts, which procedures shall include the following:

(a) The procedures and standards to be used to qualify construction managers;

(b) The procedures for preparing and submitting proposals;

(c) The procedures for evaluating proposals;

(d) The procedures for negotiations between the purchasing agency and those submitting proposals prior to the acceptance of a proposal. The procedures shall contain safeguards to preserve the confidential information and proprietary information supplied by those submitting proposals; and

(e) The procedures for awarding construction management services contracts;

(2) A request for proposals to enter into a construction management services contract shall contain the following elements:

(a) The identity of the purchasing agency;

(b) A description of the proposed public improvement;

(c) A description of the qualifications the construction manager will be required to have;

(d) The procedures to be followed for submitting proposals, the criteria for evaluation of a proposal and its relative weight, and procedures for making awards;

(e) The proposed terms and conditions for the construction management services contract, including a description of the scope of services to be provided;

(3) Notice of any request for proposals shall be advertised in accordance with the provisions of § 5-18A-14;

(4) After obtaining and evaluating proposals, a purchasing agency may accept the proposal it considers the most advantageous to the purchasing agency. Acceptance of a proposal shall be by written notice to the construction manager submitting the accepted proposal, and by simultaneously notifying in writing the other construction managers that their proposals were not accepted; and

(5) The purchasing agency shall reserve the right to reject any or all proposals submitted.Source: SL 2010, ch 31, § 83.