§ 49-41B-24 Permit for energy conversion facilities, AC/DC conversion facilities, or transmission facilities--Complete findings by commission required within year of application.

SD Codified L § 49-41B-24 (2019) (N/A)
Copy with citation
Copy as parenthetical citation

49-41B-24. Permit for energy conversion facilities, AC/DC conversion facilities, or transmission facilities--Complete findings by commission required within year of application. Within twelve months of receipt of the initial application for a permit for the construction of energy conversion facilities, AC/DC conversion facilities, or transmission facilities, the commission shall make complete findings in rendering a decision regarding whether a permit should be granted, denied, or granted upon such terms, conditions or modifications of the construction, operation, or maintenance as the commission deems appropriate.

Source: SL 1977, ch 390, § 18; SL 1980, ch 328, § 2; SL 1981, ch 341; SL 2006, ch 242, § 5; SL 2009, ch 243, § 3; SL 2015, ch 235, § 2.