49-41B-15. Commission procedure following receipt of application for permit. Within thirty days following receipt of an application for a permit, the commission shall:
(1) Schedule a public input meeting;
(2) Notify the applicant of the public input meeting; and
(3) Serve notice of the application and public input meeting upon the governing bodies of the counties and municipalities totally or partially within the area of the proposed facility.Source: SL 1977, ch 390, § 9; SL 2006, ch 242, § 4; SL 2008, ch 246, § 2; SL 2019, ch 200, § 5.