Section 11-35-3024. Additional procedures applicable to procurement of certain project delivery methods.

SC Code § 11-35-3024 (2019) (N/A)
Copy with citation
Copy as parenthetical citation

(1) Applicability. In addition to the requirements of Section 11-35-1530 (Competitive Sealed Proposals) or Section 11-35-1535 (Competitive Negotiations), the procedures in this section apply as provided in items (2), (3), and (4) below.

(2) Content of Request for Proposals. A Request for Proposals for design-build, design-build-operate-maintain, or design-build-finance-operate-maintain:

(a) must include design requirements;

(b) must solicit proposal development documents; and

(c) may, if the governmental body determines that the cost of preparing proposals is high in view of the size, estimated price, and complexity of the procurement:

(i) prequalify offerors in accordance with Section 11-35-3023 by issuing a request for qualifications in advance of the request for proposals;

(ii) select, pursuant to procedures designated in the Manual for Planning and Execution of State Permanent Improvements, a short list of responsible offerors who submit proposals determined to be reasonably susceptible of being selected for award before discussions and evaluations pursuant to Section 11-35-1530, if the number of proposals to be short-listed is stated in the Request for Proposals and prompt public notice is given to all offerors as to which proposals have been short-listed; or

(iii) pay stipends to unsuccessful offerors, if the amount of the stipends and the terms under which stipends are paid are stated in the Request for Proposals.

Subsection (2)(c)(ii) is inapplicable if competitive negotiations are conducted pursuant to Section 11-35-1535.

(3) Evaluation Factors. A Request for Proposals for design-build, design-build-operate-maintain, or design-build-finance-operate-maintain must:

(a) state the relative importance of (i) demonstrated compliance with the design requirements, (ii) offeror qualifications, (iii) financial capacity, (iv) project schedule, (v) price, or life-cycle price for design-build-operate-maintain and design-build-finance-operate-maintain procurements, and (vi) other factors, if any; and

(b) in circumstances designated in the Manual for Planning and Execution of State Permanent Improvements, require each offeror to identify an Independent Peer Reviewer whose competence and qualifications to provide that service must be an additional evaluation factor in the award of the contract.

(4) Unless excused by the State Engineer, the State Engineer's Office shall oversee the evaluation process for a procurement of construction if factors other than price are considered in the evaluation of a proposal.

HISTORY: 2008 Act No. 174, Section 4; 2019 Act No. 41 (S.530), Section 42, eff May 13, 2019.

Editor's Note

2008 Act No. 174, Section 21, provides as follows:

"This act takes effect upon approval by the Governor and applies to solicitations issued on or after January 1, 2008."

2019 Act No. 41, Section 80, provides as follows:

"SECTION 80. This act takes effect upon approval by the Governor and applies to solicitations issued after that date."

Effect of Amendment

2019 Act No. 41, Section 42, in (1), inserted "or Section 11-35-1535 (Competitive Negotiations)"; and in (2), added the last undesignated paragraph.