Section 279C.660 - Compensation when contract terminated due to public interest.

OR Rev Stat § 279C.660 (2019) (N/A)
Copy with citation
Copy as parenthetical citation

(1) Shall be determined on the basis of the contract price in the case of any fully completed separate item or portion of the work for which there is a separate or unit contract price; and

(2) May, with respect to any other work, be a percent of the contract price equal to the percentage of the work completed. [2003 c.794 §162]