(2) The evaluation must include but is not limited to the following matters:
(a) The actual project cost as compared with original project estimates;
(b) The amount of any guaranteed maximum price;
(c) The number of project change orders issued by the contracting agency;
(d) A narrative description of successes and failures during the design, engineering and construction of the project; and
(e) An objective assessment of the use of the alternative contracting process as compared to the findings required by ORS 279C.335.
(3) The evaluations required by this section:
(a) Must be made available for public inspection; and
(b) Must be completed within 30 days of the date the contracting agency accepts:
(A) The public improvement project; or
(B) The last public improvement project if the project falls within a class of public improvement contracts. [2003 c.794 §111; 2003 c.794 §112; 2007 c.764 §§22,23]