Section 227.179 - Petition for writ of mandamus authorized when city fails to take final action on land use application within 120 days; jurisdiction; notice of petition.

OR Rev Stat § 227.179 (2019) (N/A)
Copy with citation
Copy as parenthetical citation

(2) The governing body shall retain jurisdiction to make a land use decision on the application until a petition for a writ of mandamus is filed. Upon filing a petition under ORS 34.130, jurisdiction for all decisions regarding the application, including settlement, shall be with the circuit court.

(3) A person who files a petition for a writ of mandamus under this section shall provide written notice of the filing to all persons who would be entitled to notice under ORS 197.763 and to any person who participated orally or in writing in any evidentiary hearing on the application held prior to the filing of the petition. The notice shall be mailed or hand delivered on the same day the petition is filed.

(4) If the governing body does not take final action on an application within 120 days of the date the application is deemed complete, the applicant may elect to proceed with the application according to the applicable provisions of the local comprehensive plan and land use regulations or to file a petition for a writ of mandamus under this section. If the applicant elects to proceed according to the local plan and regulations, the applicant may not file a petition for a writ of mandamus within 14 days after the governing body makes a preliminary decision, provided a final written decision is issued within 14 days of the preliminary decision.

(5) The court shall issue a peremptory writ unless the governing body or any intervenor shows that the approval would violate a substantive provision of the local comprehensive plan or land use regulations as those terms are defined in ORS 197.015. The writ may specify conditions of approval that would otherwise be allowed by the local comprehensive plan or land use regulations. [1999 c.533 §10; 2003 c.150 §2]