2117 - Reports.

NY Educ L § 2117 (2019) (N/A)
Copy with citation
Copy as parenthetical citation

(1) Cost of site.

(2) Cost of site improvement including roads, parking, playfields, and utility lines to the building wall.

(3) Original furnishings, equipment and apparatus.

(4) Professional fees.

(5) Incidental costs.

(6) Total cost of building.

(7) Cost of building per pupil.

(8) Cost of building per gross square foot.

(9) Cost per gross square foot of the heating and ventilating.

(10) Cost per gross square foot of the plumbing.

(11) Cost per gross square foot of the electrical work.

(12) Square foot per pupil in the total gross area.

(13) Square foot per pupil in the net area of the regular and special classrooms.

(14) Square foot per pupil in the net area of other rooms used for educational, health, administrative or social purposes such as the cafeteria, auditorium, gymnasium, kitchen and library.

(15) Square foot per pupil of the remaining difference between the gross area and the sum of thirteen and fourteen which would include toilet rooms, general storage, corridors, stair enclosures, janitor closets, boiler rooms, building machinery rooms and the area occupied by the walls of the building.

(16) An outline of the school plan.

(17) A brief outline specification for the building construction.

(18) The name of the architect.

(19) The name of the mechanical engineer.

(20) The name of the structural engineer.

(21) Whether single or multiple bidding was used.