48:3-113 Standby charge.

4. a. Upon request to an electric public utility, electric power supplier, or basic generation service provider for standby power by a facility that supplies power to an end-use customer pursuant to section 3 of P.L.2017, c.357 (C.48:3-112) or the end-use customer of that power, the electric public utility, electric power supplier, or basic generation provider, as applicable, shall impose and assess a standby charge.

b. The Board of Public Utilities shall, within 120 days after the effective date of P.L.2017, c.357 (C.48:3-110 et seq.), establish criteria for an electric public utility, electric power supplier, or basic generation provider to assess and impose a standby charge.

L.2017, c.357, s.4.