Section 2A:44A-14 - Claimant's failure to commence action; forfeiture, liability.

NJ Rev Stat § 2A:44A-14 (2019) (N/A)
Copy with citation
Copy as parenthetical citation

2A:44A-14 Claimant's failure to commence action; forfeiture, liability.

14. a. A claimant filing a lien claim shall forfeit all rights to enforce the lien, and shall immediately discharge the lien of record in accordance with section 30 of P.L.1993, c.318 (C.2A:44A-30), if the claimant fails to commence an action in the Superior Court, in the county in which the real property is situated, to enforce the lien claim:

(1) Within one year of the date of the last provision of work, services, material or equipment, payment for which the lien claim was filed; or

(2) Within 30 days following receipt of written notice, by personal service or certified mail, return receipt requested, from the owner, community association, contractor, or subcontractor against whose account a lien claim is filed, requiring the claimant to commence an action to enforce the lien claim.

b. Any lien claimant who forfeits a lien pursuant to this section and fails to discharge that lien of record in accordance with section 30 of P.L.1993, c.318 (C.2A:44A-30), shall be liable for all court costs, and reasonable legal expenses, including, but not limited to, attorneys' fees, incurred by the owner, community association, contractor, or subcontractor, or the total costs and legal expenses of all or any combination of them, in defending or causing the discharge of the lien claim. The court shall, in addition, enter judgment against the claimant who fails to discharge the lien for damages to any of the parties adversely affected by the lien claim.

c. (Deleted by amendment, P.L.2010, c.119)

d. Any disputes arising out of the improvement which is the subject of a lien claim but which are unrelated to any action to enforce a lien claim may be brought in a separate action or in a separate count in the same action.

L.1993, c.318, s.14; amended 2010, c.119, s.11.