Section 27:7-44.2 - Relief of contractor from maintenance of completed section

NJ Rev Stat § 27:7-44.2 (2019) (N/A)
Copy with citation
Copy as parenthetical citation

27:7-44.2. Relief of contractor from maintenance of completed section

When a section of a project under contract shall have been completed prior to the completion of the entire project, the commissioner shall have authority to relieve the contractor from the maintenance of such completed section.

L.1949, c. 176, p. 566, s. 1.