1. Except as otherwise provided in subsections 2 and 4 and subsection 4 of NRS 624.622, if an owner of real property enters into a written or oral agreement with a prime contractor for the performance of work or the provision of materials or equipment by the prime contractor, the owner must:
(a) Pay the prime contractor on or before the date a payment is due pursuant to a schedule for payments established in a written agreement; or
(b) If no such schedule is established or if the agreement is oral, pay the prime contractor within 21 days after the date the prime contractor submits a request for payment.
2. If an owner has complied with subsection 3, the owner may:
(a) Withhold from any payment to be made to the prime contractor:
(1) A retention amount that, if the owner is authorized to withhold a retention amount pursuant to the agreement, must not exceed 5 percent of the amount of the payment to be made;
(2) An amount equal to the sum of the value of:
(I) Any work or labor that has not been performed or materials or equipment that has not been furnished for which payment is being sought, unless the agreement otherwise allows or requires such a payment to be made; and
(II) Costs and expenses reasonably necessary to correct or repair any work which is the subject of the request for payment and which is not materially in compliance with the agreement to the extent that such costs and expenses exceed 50 percent of the retention amount withheld pursuant to subparagraph (1); and
(3) The amount the owner has paid or is required to pay pursuant to an official notice from a state agency or employee benefit trust fund, for which the owner is or may reasonably be liable for the prime contractor or his or her lower-tiered subcontractors in accordance with chapter 608, 612, 616A to 616D, inclusive, or 617 of NRS; and
(b) Require as a condition precedent to the payment of any amount due, lien releases furnished by the prime contractor and his or her lower-tiered subcontractors and suppliers in accordance with the provisions of paragraphs (a) and (c) of subsection 5 of NRS 108.2457.
3. If, pursuant to subparagraph (2) or (3) of paragraph (a) of subsection 2 or paragraph (b) of subsection 2, an owner intends to withhold any amount from a payment to be made to a prime contractor, the owner must give, on or before the date the payment is due, a written notice to the prime contractor of any amount that will be withheld. The written notice of withholding must:
(a) Identify the amount of the request for payment that will be withheld from the prime contractor;
(b) Give a reasonably detailed explanation of the condition or the reason the owner will withhold that amount, including, without limitation, a specific reference to the provision or section of the agreement, and any documents relating thereto, and the applicable building code, law or regulation with which the prime contractor has failed to comply; and
(c) Be signed by an authorized agent of the owner.
4. A prime contractor who receives a notice of withholding pursuant to subsection 3 or a notice of objection pursuant to subparagraph (2) of paragraph (b) may:
(a) Give the owner a written notice and thereby dispute in good faith and for reasonable cause the amount withheld, or the condition or reason for the withholding; or
(b) Correct any condition or reason for the withholding described in the notice of withholding and thereafter provide written notice to the owner of the correction of the condition or reason for the withholding. The notice of correction must be sufficient to identify the scope and manner of the correction of the condition or reason for the withholding and be signed by an authorized representative of the prime contractor. If an owner receives a written notice from the prime contractor of the correction of a condition or reason for the withholding pursuant to this paragraph, the owner shall:
(1) Pay the amount withheld by the owner for that condition or reason for the withholding on or before the date the next payment is due the prime contractor; or
(2) Object to the scope and manner of the correction of the condition or reason for the withholding, on or before the date the next payment is due to the prime contractor, in a written statement which sets forth the condition or reason for the objection and which complies with subsection 3. If the owner objects to the scope and manner of the correction of a condition or reason for the withholding, the owner shall nevertheless pay to the prime contractor, along with the payment to be made pursuant to the prime contractor’s next payment request, the amount withheld for the correction of the condition or reason for the withholding to which the owner no longer objects.
5. Except as otherwise allowed in subsections 2, 3 and 4, an owner shall not withhold from a payment to be made to a prime contractor more than the retention amount.
(Added to NRS by 2001, 1619; A 2005, 1722; 2015, 2623)