90-4-1221. Requirements prior to project construction

MT Code § 90-4-1221 (2019) (N/A)
Copy with citation
Copy as parenthetical citation

90-4-1221. Requirements prior to project construction. Prior to starting construction under this part, the governmental body shall enter into a contract or contracts:

(1) with a transmission services provider to interconnect with the transmission or distribution facilities of a utility or cooperative;

(2) that ensure that all ancillary services as required by the control area operator are available to regulate the generation of electricity from the project;

(3) for the sale of electricity from the project; and

(4) with a tribal government for projects being constructed within the exterior boundaries of that tribal government's Indian reservation.

History: En. Sec. 16, Ch. 378, L. 2007.