69-8-420. Electricity supply resource procurement plans -- comment on plans

MT Code § 69-8-420 (2019) (N/A)
Copy with citation
Copy as parenthetical citation

69-8-420. (Temporary) Electricity supply resource procurement plans -- comment on plans. (1) The public utility shall develop electricity supply resource procurement plans. The plans must be submitted to the commission at intervals determined in rules adopted by the commission.

(2) An electricity supply resource procurement plan must demonstrate the public utility's achievement of the objectives provided in 69-8-419 and compliance with commission rules.

(3) The commission shall:

(a) review the electricity supply resource procurement plan;

(b) provide an opportunity to the public to comment on the plan in accordance with subsection (4); and

(c) issue written comments within 9 months after the plan is submitted to the commission that identify:

(i) any concerns of the commission regarding the public utility's compliance with commission rules; and

(ii) ways to remedy any concerns.

(4) The commission shall hold two public meetings in an area of the state encompassed by the plan. Notice of the meetings must be published once a week for 2 consecutive weeks in a newspaper of general circulation at least 30 days prior to each meeting. (Repealed effective July 1, 2020--secs. 16, 20, Ch. 449, L. 2019.)

History: En. Sec. 2, Ch. 509, L. 2003; amd. Sec. 14, Ch. 491, L. 2007; amd. Sec. 1, Ch. 422, L. 2017.