Section 436.327 Substantial completion defined.

MO Rev Stat § 436.327 (2019) (N/A)
Copy with citation
Copy as parenthetical citation

Effective 28 Aug 2002

436.327. Substantial completion defined. — The project shall be deemed to have reached substantial completion upon the occurrence of the earlier of the architect or engineer issuing a certificate of substantial completion in accordance with the terms of the contract documents or the owner accepting the performance of the full contract.

­­--------

(L. 2002 H.B. 1403)