§ 77-13-5. Excavator’s investigation of site; notice to utility of planned excavation

MS Code § 77-13-5 (2019) (N/A)
Copy with citation
Copy as parenthetical citation

(1) In addition to complying with all other applicable regulations and requirements of federal, state, county and municipal authorities, no person shall engage in excavation of any kind, before meeting the notification requirements of this chapter. Under this chapter the excavator shall:

(a) Inform himself/herself of the presence and location of any underground utility lines and underground facilities in or near the area where excavation is to be conducted;

(b) Plan and conduct the excavation to avoid or minimize interference with or damage to underground utility lines and underground facilities in or near the excavation area; maintain a clearance between any underground utility line or underground facility and the cutting edge or point of any mechanical excavating equipment, taking into account the known limit of control of such cutting edge or point, as may be reasonably necessary to avoid damage to such facility; and provide such support for underground utility lines or underground facilities in and near the excavation area, including during any backfilling operations, as may be reasonably necessary for the protection of such facilities.

(c) Except as provided in Section 77-13-11, provide not less than two (2) and not more than ten (10) working days’ advance written, electronic or telephonic notice of the commencement, extent, location and duration of the excavation work to Mississippi 811, Inc., so that Mississippi 811, Inc., operator(s) may locate and mark the location of underground utility lines and underground facilities in the excavation area.

(2) The markings provided by operators and the locate request number shall only be valid for a period of fourteen (14) calendar days from the date and time the locate request ticket is processed or entered into the system by Mississippi 811, Inc. The person responsible for the excavation project shall renew the notification with Mississippi 811, Inc., at least two (2) and not more than three (3) working days prior to this expiration date and shall continue to renew such notification in the same manner throughout the duration of the excavation. Such renewal notice shall be valid for a period of fourteen (14) calendar days from the date and time the renewal locate request is processed or entered into the system by Mississippi 811, Inc.

(3) Compliance with the notice requirements of this section shall not be required of: (a) persons plowing less than twenty-four (24) inches in depth for agricultural purposes; (b) persons who are moving or otherwise displacing, by hand, earth, rock or other material or mass of material on or below the ground at a depth of less than twelve (12) inches on property they own; and (c) persons, other than the property owner, who are moving or otherwise displacing, by hand, earth, rock or other material or mass of material on or below the ground at a depth of less than twelve (12) inches, except when such excavation is in a clearly marked underground facility right-of-way.

(4) A person may make a written, electronic or telephonic design information request to Mississippi 811, Inc., so that owners and operators of utilities may locate underground utility lines and underground facilities in the design information area. The design information request shall contain the name, address, and telephone number of the person making the request, the type of project planned, and a description of the area to be located with sufficient particularity to enable the utility owner or operator to ascertain the precise tract or parcel of land involved.