Section 324.5309 Segmenting Sewage Treatment Work Project.

MI Comp L § 324.5309 (2019) (N/A)
Copy with citation
Copy as parenthetical citation

Sec. 5309.

To ensure that a disproportionate share of available funds for a given fiscal year is not committed to a single sewage treatment work project or stormwater project, the department may segment a sewage treatment work project if either of the following criteria is present:

(a) The cost of the proposed project is more than 30% of the amount available in the fund.

(b) Upon application of a municipality, the department has approved a municipality's application for segmenting a project.

History: 1994, Act 451, Eff. Mar. 30, 1995 Popular Name: Act 451Popular Name: NREPA