45A.181 Requirements for request for proposal when capital project is to be constructed utilizing the design-build construction method. When a capital project is to be constructed utilizing the design-build construction method in accordance with KRS 45A.180, the percentage of scoring to be attributed to the guaranteed maximum price shall be stated in the request for proposal. A request for proposal may allow for the payment of stipends for the technical proposal phase provided that the amount of the stipends and the terms under which stipends are to be paid are stated in the request for proposal. Effective: June 24, 2003 History: Created 2003 Ky. Acts ch. 98, sec. 8, effective June 24, 2003.