16-1907 Provisions waiving right to collect damages for delays, void, unenforceable.

KS Stat § 16-1907 (2018) (N/A)
Copy with citation
Copy as parenthetical citation

16-1907. Provisions waiving right to collect damages for delays, void, unenforceable. Any provision in a contract that purports to waive the rights of a party to the contract to collect damages for delays caused by another party to the contract shall be void, unenforceable and against public policy. This provision is not intended to create a contract between parties where a contract did not otherwise exist.

History: L. 2007, ch. 163, § 7; July 1.