8-1-8.7-10. Construction of electric generating facilities; additional certification; joint applications

IN Code § 8-1-8.7-10 (2019) (N/A)
Copy with citation
Copy as parenthetical citation

Sec. 10. (a) This chapter does not relieve a public utility of the duty to obtain a certificate under IC 8-1-8.5 if the utility is proposing the use of clean coal technology as a part of the construction of an electric generating facility.

(b) A public utility seeking a certificate under IC 8-1-8.5 and this chapter for one (1) project may file a joint application for both certificates. If a joint application is filed, the commission shall jointly consider both certificates.

As added by P.L.105-1989, SEC.4.