36-1-9.5-22. New statement demand by entity; effect of noncompliance; incomplete or false information in prequalification application

IN Code § 36-1-9.5-22 (2019) (N/A)
Copy with citation
Copy as parenthetical citation

Sec. 22. (a) An entity may at any time during which a certificate of qualification is in effect demand a new statement. If a contractor does not provide a new statement not later than sixty (60) days after the request is made, the entity may void the contractor's certificate of qualification.

(b) If a contractor fails to provide complete and true information in an application, the application for prequalification shall be rejected.

As added by P.L.85-1991, SEC.3.