Sec. 6. (a) This chapter applies if the works board of a municipality wants to acquire property for the use of the municipality or to open, change, lay out, or vacate a street, an alley, or a public place in the municipality, including a proposed street or alley crossings of railways or other rights-of-way. However, this chapter does not apply if a municipality wants to acquire the property of a public utility (as defined in IC 8-1-2-1).
(b) The works board must adopt a resolution that the municipality wants to acquire the property. The resolution must describe the property that may be injuriously or beneficially affected. The board shall have notice of the resolution published in a newspaper of general circulation published in the municipality once each week for two (2) consecutive weeks. The notice must name a date, at least ten (10) days after the last publication, at which time the board will receive or hear remonstrances from persons interested in or affected by the proceeding.
(c) The works board shall consider the remonstrances, if any, and then take final action, confirming, modifying, or rescinding its original resolution. This action is conclusive as to all persons.
[Pre-2002 Recodification Citation: 32-11-1.5-3.]
As added by P.L.2-2002, SEC.9. Amended by P.L.172-2009, SEC.6.