13-18-22-8. Department action on wetland permits; effective dates of permits; amended permit application

IN Code § 13-18-22-8 (2019) (N/A)
Copy with citation
Copy as parenthetical citation

Sec. 8. (a) Subject to subsection (f), the department shall make a decision to issue or deny an individual permit under section 3 or 7(b)(1) of this chapter not later than one hundred twenty (120) days after receipt of the completed application. If the department fails to make a decision on a permit application by the deadline under this subsection or subsection (f), a permit is considered to have been issued by the department in accordance with the application.

(b) A general permit under section 4 of this chapter becomes effective with respect to a proposed wetland activity that is within the scope of the general permit on the thirty-first day after the department receives a notice of intent from the person proposing the wetland activity that the wetland activity be authorized under the general permit.

(c) Except as provided in subsection (d), a permit to undertake a wetland activity in a Class I wetland under section 7(b)(2) of this chapter is considered to have been issued to an applicant on the thirty-first day after the department receives a notice of registration submitted under section 7(b)(2) of this chapter if the department has not previously authorized the wetland activity.

(d) The department may deny a registration for a permit for cause under subsection (c) before the period specified in subsection (c) expires.

(e) The department must support a denial under subsection (a) or (d) by a written statement of reasons.

(f) The department may notify the applicant that the completed application referred to in subsection (a) is deficient. If the department fails to give notice to the applicant under this subsection not later than fifteen (15) days after the department's receipt of the completed application, the application is considered not to have been deficient. After receipt of a notice under this subsection, the applicant may submit an amended application that corrects the deficiency. The department shall make a decision to issue or deny an individual permit under the amended application within a period that ends a number of days after the date the department receives the amended application equal to the remainder of:

(1) one hundred twenty (120) days; minus

(2) the number of days the department held the initial application before giving a notice of deficiency under this subsection.

As added by P.L.282-2003, SEC.38. Amended by P.L.52-2004, SEC.10.