§ 2–356.02. Source selection methods assigned to project delivery methods.

DC Code § 2–356.02 (2019) (N/A)
Copy with citation
Copy as parenthetical citation

(a) This section specifies the source selection methods applicable to procurements for the project delivery methods identified in § 2-356.01, except as provided in §§ 2-354.04, 2-354.05, 2-354.07, 2-354.08, 2-354.11, and 2-354.12.

(b)(1) The qualifications-based selection process set forth in § 2-356.04 shall be used to procure architectural and engineering services in design-bid-build procurements.

(2) Competitive sealed bidding, as set forth in § 2-354.02, shall be used to procure construction in design-bid-build procurements, except where rules authorize the use of competitive sealed proposals, as set forth in § 2-354.03, for contracts for construction management at-risk.

(c) Contracts for operations and maintenance shall be procured as set forth in § 2-354.01.

(d) Contracts for design-build shall be procured by competitive sealed proposals, as set forth in § 2-354.03.

(e) Contracts for design-build-operate-maintain shall be procured by competitive sealed proposals, as set forth in § 2-354.03.

(f) Contracts for design-build-finance-operate-maintain shall be procured by competitive sealed proposals, as set forth in § 2-354.03.

(Apr. 8, 2011, D.C. Law 18-371, § 602, 58 DCR 1185.)

Stadiums, construction, see §§ 10-1601.03, 10-1601.05.