(a) No mechanic's lien may attach to any building or its appurtenances, or to the land on which the same stands, or any lot, or any plot of land, in favor of any person, to a greater amount in the whole than the price which the owner agreed to pay for the building and its appurtenances or the development of any such lot, or the development of any such plot of land.
(b) When there are several claimants and the amount of their united claims exceeds that price, the claimants, other than the original contractor, shall be first paid in full, if the amount of that price is sufficient for that purpose; but, if not, it shall be apportioned among the claimants having the liens, other than the original contractor, in proportion to the amount of the debts due them respectively; and the court having jurisdiction thereof, on application of any person interested, may direct the manner in which the claims shall be paid.
(c) In determining the amount to which any lien or liens may attach upon any land or building, or lot or plot of land, the owner of the land or building or lot or plot of land shall be allowed whatever payments he has made, in good faith, to the original contractor or contractors, before receiving notice of the lien or liens. No payments made in advance of the time stipulated in the original contract may be considered as made in good faith, unless notice of intention to make the payment has been given in writing to each person known to have furnished materials or rendered services at least five days before the payment is made.
(1949 Rev., S. 7220; P.A. 74-310, S. 4; P.A. 79-602, S. 92.)
History: P.A. 74-310 applied provisions with respect to lots, plots of land and development of such land; P.A. 79-602 divided section into Subsecs., substituted “may” for “shall” and “the”, etc. for “such” and made other slight changes in wording.
Owner is to be allowed for bona fide payments to original contractor before notice, though made in advance. 27 C. 578. Owner cannot waive defect in notice of intent so as to make lien valid as against others claiming liens. 42 C. 541. Owner not allowed for payments made after notice to him by subcontractor, although he had, before such notice, verbally guaranteed contractor's debts, in performance of which guaranty he made such payments. 43 C. 14. Limitation of amount of liens generally. 73 C. 519. Effect of abandonment of work by contractor. Id., 452; 82 C. 244; 87 C. 686; 89 C. 254. Effect of alteration in original contract; of payment made before notice of lien; of payment made in advance of time agreed on. 74 C. 493; 81 C. 502; 89 C. 254; 131 C. 643. Payment of subcontractor by contractor will not defeat lien of one to whom former has sublet part of work. 76 C. 107. Subcontractor has no greater rights than his principal. 81 C. 632; 82 C. 244; 96 C. 225. Effect of direct payments by mortgagee holding advance payment mortgage to contractor, at request of mortgagor. 82 C. 244. Effect of contract providing for payments as work progresses under which weekly payments are made and contract price is fully paid. 84 C. 487. What constitutes “notice” of subcontractor's lien. Id.; 91 C. 712. What constitutes knowledge in provision for advance payments. 89 C. 262. Right of subcontractors where one gives notice, owner thereafter makes payments on contract, and then others give notice. 92 C. 482. Duty of owner as to withholding payments after receiving notice. Id., 485. No priority between subcontractors under same original contractor. 99 C. 343; 108 C. 243. Cited. 109 C. 364; Id., 554; 113 C. 10; 115 C. 199. Finding of fraud between owner and principal contractor. 111 C. 132. Priority of materialmen over contractor not removed by assumption by owner to pay them. 116 C. 277. In action to foreclose lien of subcontractor, original contractor a necessary party. 118 C. 614. Payments made in advance of the time when they are due under the contract and without notice to the lienor are ineffective as to him in reducing the amount due on the contract. 143 C. 146. Cited. 147 C. 351; 168 C. 371; 169 C. 76; 180 C. 501; 181 C. 592; 182 C. 568. Challenge by general contractor to constitutionality of mechanic's lien statutes discussed. 185 C. 583.
Cited. 27 CA 199; 39 CA 122. Defendant, despite having paid general contractor the original contract price in full, still owed general contractor for “extras” and therefore a lienable fund existed and subcontractor's lien was not invalid. 136 CA 184.
Cited. 15 CS 360; 23 CS 380.
Cited. 2 Conn. Cir. Ct. 620. Only payments made to original contractor in good faith before notice of subcontractor's lien are allowed owner. 6 Conn. Cir. Ct. 512.