Section 16-50cc - Reconfiguration or burial of electric transmission facility.

CT Gen Stat § 16-50cc (2019) (N/A)
Copy with citation
Copy as parenthetical citation

If legislation adopted on or after January 1, 2004, results in the reconfiguration or burial of a proposed facility described in subdivision (1) of subsection (a) of section 16-50i, all prudent costs incurred by an electric distribution company, as defined in section 16-1, associated with the reconfiguration or burial shall be deemed to be reasonable pursuant to sections 16-19 and 16-19e and shall be recovered by the electric distribution company in its rates.

(P.A. 04-246, S. 11.)

History: P.A. 04-246 effective June 3, 2004, and applicable to applications for a certificate of environmental compatibility and public need that was originally filed on or after October 1, 2003, for which the Connecticut Siting Council has not rendered a decision upon the record prior to June 3, 2004.