(1) The department shall describe in the specifications for the transportation project the particular design-build contract and selection procedures to be used in awarding such contract, including but are not limited to the following:
(a) A scope of work statement that defines the transportation project and provides prospective design-build firms with sufficient information regarding the department's requirements for the transportation project;
(b) If the department uses an adjusted score design-build contract process to select a design-build firm, a scope of work statement that is flexible and that identifies the end result that the department wants to achieve. The department may determine the adjustment factors and methods it will use to adjust scores and shall state such factors and methods in the specifications for the transportation project. The department may also provide a general concept of the transportation project to potential design-build firms. Adjusted score design-build procedures shall consist of the following two phases:
(I) In the first phase, the department shall issue a request for qualifications within the time specified in section 43-1-1405 to solicit proposals that include information on the design-build firm's qualifications and its technical approach to the proposed transportation project. The department shall include appropriate evaluation factors in the request for qualifications, including the factors set forth in section 24-30-1403 (2), C.R.S. The department shall not include cost-related or price-related factors in the request for qualifications. In accordance with the time requirements specified in the department's rules, the department shall develop a short list of the highest qualified design-build firms from the proposals submitted in response to the request for qualifications.
(II) In the second phase, the department shall issue a request for proposals to the design-build firms included on the short list developed pursuant to subparagraph (I) of this paragraph (b) in accordance with the time requirements specified in the department's rules. The request for proposals shall include:
(A) A request to separately submit a sealed technical proposal and a sealed cost proposal for the transportation project;
(B) The required content of the technical proposal to be submitted by the design-build firm, including design concepts for the transportation project, the proposedsolutions to the requirements addressed in the department's scope of work statement, or both;
(C) Any other evaluation factors the department considers appropriate, including the estimated cost of the transportation project; and
(D) Any formula the department determines is appropriate to adjust the total score of a design-build firm's proposal.
(2) Except as provided in this subsection (2), the department shall allow the preference to Colorado residents provided in section 24-103-908 in awarding an adjusted score design-build contract pursuant to this part 14. In evaluating and selecting a proposal for a design-build contract under this part 14, the department shall assign greater value to a proposal in proportion to the extent such proposal commits to using Colorado residents to perform work on the transportation project. If, however, the department determines that compliance with this subsection (2) may cause the denial of federal moneys that would otherwise be available for the transportation project or if such compliance would otherwise be inconsistent with the requirements of federal law, the department shall suspend the preference granted under this subsection (2) only to the extent necessary to prevent denial of federal moneys or to eliminate the inconsistency with federal law.
(3) The department may use any basis for awarding a design-build contract pursuant to this part 14 that it deems appropriate so long as the basis for awarding such contract is adequately described in the specifications for the transportation project or the request for proposals. Such basis may include awarding a contract to the design-build firm whose proposal provides the best value to the department.
(4) The department may cancel any request for qualifications, request for proposals, or other solicitation issued pursuant to this part 14 or may reject any or all proposals in whole or in part when the department determines that such cancellation or rejection is in the best interest of the department.
(5) If the department awards a design-build contract pursuant to this part 14, the department shall execute a design-build contract with the successful design-build firm and shall give notice to said firm to commence work on the transportation project.