§ 31-25-518. Provisions to be inserted

CO Rev Stat § 31-25-518 (2018) (N/A)
Copy with citation
Copy as parenthetical citation

Every contract shall provide that it is subject to the provisions of the laws under which the municipality exists and of the ordinance authorizing the improvement; that the aggregate payment thereon shall not exceed the amount appropriated; that, upon ten days' written notice by the mayor to the contractor, the work under such contract, without cost or claim against the municipality, may be suspended for substantial cause; and that, upon complaint by any owner of land to be assessed for the improvement that the improvement is not being constructed in accordance with the contract, the governing body may consider the complaint and make such order in the premises as shall be just. Such order shall be final.