Section 21168.9.

CA Pub Res Code § 21168.9 (2019) (N/A)
Copy with citation
Copy as parenthetical citation

(a) If a court finds, as a result of a trial, hearing, or remand from an appellate court, that any determination, finding, or decision of a public agency has been made without compliance with this division, the court shall enter an order that includes one or more of the following:

(1) A mandate that the determination, finding, or decision be voided by the public agency, in whole or in part.

(2) If the court finds that a specific project activity or activities will prejudice the consideration or implementation of particular mitigation measures or alternatives to the project, a mandate that the public agency and any real parties in interest suspend any or all specific project activity or activities, pursuant to the determination, finding, or decision, that could result in an adverse change or alteration to the physical environment, until the public agency has taken any actions that may be necessary to bring the determination, finding, or decision into compliance with this division.

(3) A mandate that the public agency take specific action as may be necessary to bring the determination, finding, or decision into compliance with this division.

(b) Any order pursuant to subdivision (a) shall include only those mandates which are necessary to achieve compliance with this division and only those specific project activities in noncompliance with this division. The order shall be made by the issuance of a peremptory writ of mandate specifying what action by the public agency is necessary to comply with this division. However, the order shall be limited to that portion of a determination, finding, or decision or the specific project activity or activities found to be in noncompliance only if a court finds that (1) the portion or specific project activity or activities are severable, (2) severance will not prejudice complete and full compliance with this division, and (3) the court has not found the remainder of the project to be in noncompliance with this division. The trial court shall retain jurisdiction over the public agency’s proceedings by way of a return to the peremptory writ until the court has determined that the public agency has complied with this division.

(c) Nothing in this section authorizes a court to direct any public agency to exercise its discretion in any particular way. Except as expressly provided in this section, nothing in this section is intended to limit the equitable powers of the court.

(Amended by Stats. 1993, Ch. 1131, Sec. 9. Effective January 1, 1994.)