Sec. 09.45.894. Additional construction defects; additional notice of claim required.

AK Stat § 09.45.894 (2019) (N/A)
Copy with citation
Copy as parenthetical citation

A court action for a defect that is discovered after a claimant has provided a construction professional with a notice of claim required in AS 09.45.881 - 09.45.899 may not be commenced until the claimant has complied with the provisions of AS 09.45.881 - 09.45.899.