Applications must include a network design that demonstrates the project's technical feasibility. The network design must fully support the delivery of service at the broadband lending speed, together with any other services to be provided. In measuring speed, the Agency will take into account industry and regulatory standards. The design must demonstrate that the project will be complete within three years from the day the Agency notifies the applicant that loan funds are available and must include the following items:
A detailed description of the proposed technology that will be used to provide service at the broadband lending speed. This description must clearly demonstrate that all households in the proposed funded service area will be offered service at the broadband lending speed;
A detailed description of the existing network. This description should provide a synopsis of the current network infrastructure;
A detailed description of the proposed network. This description should provide a synopsis of the proposed network infrastructure;
A description of the approach and methodology for monitoring ongoing service delivery and service quality for the services being deployed;
Estimated project costs detailing all facilities that are required to complete the project. These estimated costs must be broken down to indicate costs associated with each proposed service area and must specify how Agency and non-Agency funds will be used to complete the project;
A construction build-out schedule of the proposed facilities by service area on a quarterly basis. The build-out schedule must include:
A description of the work force that will be required to complete the proposed construction;
A timeline demonstrating project completion within three years and four months from the date of the loan contract;
Detailed information showing that all households within the proposed funded service area will be offered service at the broadband lending speed when the system is complete; and
Detailed information showing that construction of the proposed facilities will start within six months from the date the Agency notifies the borrower that loan funds are available.
A depreciation schedule for all facilities financed with loan and non-loan funds;
Environmental review documentation prepared in accordance with 7 CFR part 1970; and
Any other system requirements required by the Administrator through a notice published in the Federal Register.
The network design must be prepared by a registered Professional Engineer with telecommunications experience or by qualified personnel on the applicant's staff. If the network design is prepared by the applicant's staff, the application must clearly demonstrate the staff's qualifications, experience, and ability to complete the network design. To be considered qualified, staff must have at least three years of experience in designing the type of broadband system proposed in the application.