§ 1410.22 - CRP conservation plan.

Copy with citation
Copy as parenthetical citation

The producer must obtain a CRP conservation plan that complies with CCC guidelines and is approved by the conservation district for the land to be entered in CRP. If the conservation district declines to review the CRP conservation plan, or disapproves the conservation plan, such approval may be waived by the Deputy Administrator.

The practices and management activities included in the CRP conservation plan and agreed to by the participant must cost-effectively reduce erosion necessary to maintain the productive capability of the soil, improve water quality, protect wildlife or wetlands, protect a public well head, improve grassland, or achieve other environmental benefits as applicable. The producer must undertake management activities on the land as needed throughout the term of the CRP contract to implement the conservation plan.

If applicable, a tree planting plan or forest stewardship plan must be developed and included in the CRP conservation plan. Such tree planting plan may allow up to 3 years to complete plantings if 10 or more acres of hardwood trees are to be established.

If applicable, the CRP conservation plan shall address the goals included in the conservation priority area designation authorized under § 1410.8.

All CRP conservation plans and revisions of such plans shall be subject to the approval of the Deputy Administrator.

For general signup and continuous signup contracts except grasslands, mid-contract management must be conducted to implement management activities, such as disking and prescribed burning according to an approved conservation plan, as part of the CRP contractual obligation on all contracts entered into under general signup and continuous signup, as specified in § 1410.30.