§ 175.215 - What is BIA's procedure for adjusting electric power rates?

Copy with citation
Copy as parenthetical citation

Except for purchased power costs, if we determine electric power rates need to be adjusted, we will:

Hold public meetings and notify you of their respective time, date, and location by newspaper notice and a notice posted in the utility office serving you;

Provide you notice at least 15 days prior to the meeting;

Provide you a description of the proposed rate adjustment;

Provide you information on how, where, and when to submit comments on our proposed rate adjustment;

Make a final determination on the proposed rate adjustment after all comments have been received, reviewed, and evaluated; and

Publish the proposed rate adjustment and the final rate in the Federal Register if we determine the rate adjustment is necessary.