A WSR lease must provide for the installation of a facility and associated infrastructure of a size and magnitude necessary for the generation and delivery of electricity, in accordance with § 162.019. These facilities and associated infrastructure are considered permanent improvements. A resource development plan must be submitted for approval with the lease under § 162.563(h).
If the parties agree to any of the following changes to the resource development plan after lease approval, they must submit the revised plan to BIA for the file:
Location of permanent improvements;
Type of permanent improvements; or
Delay of 90 days or more in any phase of development.