The sponsor or planning agency shall monitor performance under the project to ensure that—
Time schedules are being met;
Work units projected by time periods are being accomplished; and,
Other performance goals are being achieved.
Reviews shall be made for—
Each item of development or work element included in the project; and
All other work to be performed as a condition of the grant agreement.
Airport development. Unless otherwise requested by the Administrator, the sponsor of a project for airport development shall submit a performance report, on an annual basis, that must include—
A comparison of actual accomplishments to the goals established for the period, made, if applicable, on a quantitative basis related to cost data for computation of unit costs;
The reasons for slippage in each case where an established goal was not met; and
Other pertinent information including, when appropriate, an analysis and explanation of each cost overrun and high unit cost.
Airport planning. The sponsor of a project for airport master planning or a planning agency conducting a project for airport system planning shall submit a performance report, on a quarterly basis, that must include:
A comparison of actual accomplishments to the goals established for the period, made, if applicable, on a quantitative basis related to costs for computation of work element costs;
Reasons for slippage in each case where an established goal was not met; and
Other pertinent information including, when appropriate, an analysis and explanation of each cost overrun and high work element cost.