Purpose. Each Standby Support Contract shall include a provision setting forth an agreement between the parties in which the Department shall provide compensation for covered costs incurred by a sponsor for covered events that result in a covered delay of full power operation of an advanced nuclear facility.
Covered facility. Each Standby Support Contract shall include a provision of coverage only for an advanced nuclear facility which is not a federal entity. Each Standby Support Contract shall also include a provision to specify the advanced nuclear facility to be covered, along with the reactor design, and the location of the advanced nuclear facility.
Sponsor contribution. Each Standby Support Contract shall include a provision to specify the amount that a sponsor has contributed to funding each type of account.
Maximum compensation. Each Standby Support Contract shall include a provision to specify that the Program Administrator shall not pay compensation under the contract:
In an aggregate amount that exceeds the amount of coverage up to $500 million each for the initial two reactors or up to $250 million each for the subsequent four reactors;
In an amount for principal or interest costs for which the loan costs exceed the amount deposited in the Program Account; and
In an amount for incremental costs that exceed the amount deposited in the Grant Account.
Term. Each Standby Support Contract shall include a provision to specify the date at which the contract commences as well as the term of the contract. The contract shall enter into force on the date it has been signed by both the sponsor and the Program Administrator. Subject to the cancellation provisions set forth in paragraph (f) of this section, the contract shall terminate when all claims have been paid up to the full amounts to be covered under the Standby Support Contract, or all disputes involving claims under the contract have been resolved in accordance with subpart D of this part.
Cancellation provisions. Each Standby Support Contract shall provide for cancellation in the following circumstances:
If the sponsor abandons construction, and the abandonment is not caused by a covered event or force majeure, the Program Administrator may cancel the Standby Support Contract by giving written notice thereof to the sponsor and the parties have no further rights or obligations under the contract.
If the sponsor does not require continuing coverage under the contract, the sponsor may cancel the Standby Support Contract by giving written notice thereof to the Program Administrator and the parties have no further rights or obligations under the contract.
For such other cause as agreed to by the parties.
Termination by sponsor. Each Standby Support Contract shall include a provision that prohibits a sponsor or any related party from executing another Standby Support Contract, if the sponsor elects to terminate its original existing Standby Support Contract, unless the sponsor has cancelled or terminated construction of the reactor covered by its original existing Standby Support Contract.
Assignment. Each Standby Support Contract shall include a provision on assignment of a sponsor's rights and obligations under the contract and assignment of payment of covered costs. The Program Administrator shall permit the assignment of payment of covered costs with prior written notice to the Department. The Program Administrator shall permit assignment of rights and obligations under the contract with the Department's prior approval. The sponsor may not assign its rights and obligations under the contract without the prior written approval of the Program Administrator and any attempt to do so is null and void.
Claims administration. Each Standby Support Contract shall include a provision to specify a mechanism for administering claims pursuant to the procedures set forth in subpart C of this part.
Dispute resolution. Consistent with the Administrative Dispute Resolution Act, each Standby Support Contract shall include a provision to specify a mechanism for resolving disputes pursuant to the procedures set forth in subpart D of this part.
Re-estimation. Consistent with the Federal Credit Reform Act (FCRA) of 1990, the sponsor shall provide all needed documentation as required in § 950.12 to allow the Department to annually re-estimate the loan cost needed in the financing account as that term is used in 2 U.S.C. 661a(7) and funded by the Program Account. “The sponsor is neither responsible for any increase in loan costs, nor entitled to recoup fees for any decrease in loan costs, resulting from the re-estimation conducted pursuant to FCRA.