No amounts authorized to be appropriated or otherwise made available for the Department of Energy by the Floyd D. Spence National Defense Authorization Act for Fiscal Year 2001 (as enacted into law by Public Law 106–398) or any other Act may be obligated or expended for purposes of commencing the decommissioning of the F–canyon facility at the Savannah River Site until the Secretary of Energy submits to the Committee on Armed Services of the Senate and the Committee on Armed Services of the House of Representatives, and the Defense Nuclear Facilities Safety Board, a report setting forth—
(1) an assessment of whether or not all materials present in the F–canyon facility as of the date of the report that required stabilization have been safely stabilized as of that date;
(2) an assessment of whether or not the requirements applicable to the F–canyon facility to meet the future needs of the United States for fissile materials disposition can be met through full use of the H–canyon facility at the Savannah River Site; and
if it appears that one or more of the requirements described in paragraph (2) cannot be met through full use of the H–canyon facility—
(A) an identification by the Secretary of each such requirement that cannot be met through full use of the H–canyon facility; and
(B) for each requirement so identified, the reasons why such requirement cannot be met through full use of the H–canyon facility and a description of the alternative capability for fissile materials disposition that is needed to meet such requirement.
(Pub. L. 107–314, div. D, title XLIV, § 4454, formerly Pub. L. 106–398, § 1 [div. C, title XXXI, § 3137(b)], Oct. 30, 2000, 114 Stat. 1654, 1654A–460; renumbered Pub. L. 107–314, div. D, title XLIV, § 4454, and amended Pub. L. 108–136, div. C, title XXXI, §§ 3115(b), 3141(g)(24), Nov. 24, 2003, 117 Stat. 1745, 1770; Pub. L. 113–291, div. C, title XXXI, § 3142(i), Dec. 19, 2014, 128 Stat. 3900.)