With respect to a major defense acquisition program, the Secretary of Defense shall ensure that an independent technical risk assessment is conducted—
(1) before any decision to grant Milestone A approval for the program pursuant to section 2366a of this title, that identifies critical technologies and manufacturing processes that need to be matured; and
(2) before any decision to grant Milestone B approval for the program pursuant to section 2366b of this title, any decision to enter into low-rate initial production or full-rate production, or at any other time considered appropriate by the Secretary, that includes the identification of any critical technologies or manufacturing processes that have not been successfully demonstrated in a relevant environment.
The Secretary shall issue guidance and a framework for categorizing the degree of technical and manufacturing risk in a major defense acquisition program.
(Added Pub. L. 114–328, div. A, title VIII, § 807(a)(1), Dec. 23, 2016, 130 Stat. 2261.)