A contracting officer may award a sole source contract to an SDVO SBC only when the contracting officer determines that:
None of the provisions of §§ 125.21 or 125.22 apply;
The anticipated award price of the contract, including options, will not exceed:
$6,500,000 for a contract assigned a manufacturing NAICS code, or
$4,000,000 for all other contracts;
A SDVO SBC is a responsible contractor able to perform the contract; and
Contract award can be made at a fair and reasonable price.